Modernisation of Hirschhorn Navigation Lock, Heidelberg, Germany
Released on = September 12, 2006, 4:07 am
Press Release Author = PERI GmbH
Industry = Construction
Press Release Summary = Safe load transfer and fast moving times MULTIPROP tower system as horizontal bracing
Press Release Body = PERI engineers developed an unusual but efficient formwork solution for the repair of the Hirschhorn navigation lock on the Neckar river. The PERI MULTIPROP system was used for reinforcing two VARIO wall formwork elements in a horizontal direction.
Repairing the 150 metre long lock chamber required a 40 cm thick facing made of reinforced concrete. For constructing the 7.15 metre long and 9.50 metre high sections, the contractors used the so-called back-step procedure - concreting was done with the alternating sequential method. The PERI solution involved one 70 square metre large element for both the left and right lock walls using the PERI VARIO GT 24 variable girder wall formwork system. Horizontally positioned MULTIPROP towers connected with system frames took on the task of bracing the formwork elements. Both systems were adapted perfectly to each other by engineers from PERI´s Stuttgart office. In this way, the safe transfer of loads was guaranteed for the entire lock width of twelve metres.
The entire bracing construction could be divided into three units for moving with the crane. Thus, only five lifts were necessary to complete the re-positioning process: three for the MULTIPROP units and two for the VARIO wall formwork elements. Logical operational sequences and simple assembly steps ensured that only four men were needed for striking, moving and shuttering.
For safe and efficient shifting of the PERI VARIO GT 24 large area elements and the MULTIPROP tower units, PERI designed special cross-beam constructions to ensure even load distribution. Whereas the moving aid for the formwork was firmly connected to the VARIO elements, the MULTIPROP bracing was moved in sections with the help of the cross-beams. The three transportable units could be detached in a longitudinal direction and then attached to the cross-beam. Two cross-bars at the base and vertical ties ensured that the braced MRK frame did not have to carry any tensile force through the dead weight. The nine metre high and, including load-carrying equipment, impressive 8.6 tonne bracing construction could be safely moved from cycle to cycle without any deformation and distortion.
The Hirschhorn lock installation on the River Neckar was built in 1927 in the course of a regional waterway development project. In 1958, a left chamber was added. Significant damage to the right chamber meant that fundamental re-development work had to be carried out. During the entire construction period, lock operations continued with the second chamber only. For stabilizing the lock walls, 25 m long permanent anchors were installed which transfer almost 3,000 kN into the bedrock.
Re-prints are free of charge quoting \"Source: PERI GmbH\". Please send a copy to the PERI Editorial Office.
PERI Editorial Team Tel.: +49/ 73 09/ 9 50-1 18 Fax: +49/ 73 09/ 9 51-1 18 redaktion@peri.de www.peri.de/ww/en/pub/presse/sept_01_06.cfm
PERI was founded in 1969 and is today one of the leading providers of formwork and scaffolding systems. Along with the headquarters in Weißenhorn, Germany, the company has 42 international subsidiaries and 70 stock yards around the world. The company has over 4.000 employees of which 700 are engineers (as of 2005). 2005 revenues were more than 760 million Euros.